11111 Mallory test st, Hampton, VA · Team: TBD · Total Days: 2.5
Scheduled: Scheduled: TBD
11111 Mallory test st — Kitchen remodel 11111 Mallory test st, Hampton, VA · Team: TBD · Total Days: 2.5
Total time allowance: 2.5 day(s)
Assign the crews — pick a contractor and the days per service
Ludy: assign a contractor to each service and set either the days or the
amount you pay for that service. Allowance is that service's share of the total time.
Service / trade
Contractor
Days
Demolition
Remove existing kitchen finishes, cabinets, flooring and any damaged substrate.
Structural
Beam and support work for the new kitchen layout.
Framing
Frame new openings, soffits and walls per plan.
Drywall — rough install
Hang and finish drywall in the remodeled areas.
Doors & trim
Install interior doors, casing and trim.
Windows
Window replacement in the kitchen area.
Interior painting
Paint walls, ceilings and trim in the remodeled areas.
Cabinet
Install new cabinetry (uppers, lowers, island with built-in storage).
Flooring
Install new flooring across the remodeled kitchen / dining / living area.
Appliances
Install new appliances.
Plumbing — rough and final
Rough-in and final plumbing for the new layout.
Electrical — rough and final
Rough-in and final electrical, island outlets and charging station.
Total time allowance2.5 day(s)
Pick the crew per service and the days (0 allowed) — it saves here.
Work description
Remove existing kitchen finishes, cabinets, flooring and any damaged substrate.
Beam and support work for the new kitchen layout.
Frame new openings, soffits and walls per plan.
Hang and finish drywall in the remodeled areas.
Install interior doors, casing and trim.
Window replacement in the kitchen area.
Paint walls, ceilings and trim in the remodeled areas.
Install new cabinetry (uppers, lowers, island with built-in storage).
Install new flooring across the remodeled kitchen / dining / living area.
Install new appliances.
Rough-in and final plumbing for the new layout.
Rough-in and final electrical, island outlets and charging station.
Scope & time allowance
Scope of work
Time allowance
Demolition
0.5
Structural
0.5
Framing
0.25
Drywall — rough install
0.25
Doors & trim
0.25
Windows
0.25
Interior painting
0.25
Cabinet
0.25
Flooring
0.25
Appliances
0.1
Plumbing — rough and final
0.25
Electrical — rough and final
0.25
Total time allowance2.5 day(s)
TERMS & CONDITIONS Work per accepted Estimate #1376 (copy of the 1701 North Mallory St project). Warranty: 12 months workmanship. TEST COPY — sample work order for training, no pricing on this page.
Internal work order — time allowances in crew days, no pricing on this page.